Location: Canberra, ACT
Configuration: Stormceptor Class 1 S.400/100.C1.2C with Oil Alert System
Inlet/Outlet size: 900RCP
Treatment Flow Rate: 150LPS
Total Volume: 53,300L
Excavation depth: 3.8m
The Challenge
The airport is located near to Lake Burley Griffin, so there is a need to treat and monitor all contaminated stormwater runoff from the tarmac without discharging hydrocarbons or nutrient loads to the lake.
Our Solution
SPEL was able to supply a Class 1 Stormceptor with Oil Alert System which treats and monitors the entire Airport terminal catchment.
This also ensures stormwater is safely discharged to Lake Burley Griffin whilst maintaining a strict Stormwater quality discharge and with relatively low maintenance costs.